1218c33aa4
Add the fabrication spec and document the RF constraints a reviewer flagged
routing-8layer-restack
onur
2026-09-01 18:19:22 +03:00
-
791ca5c9fa
Restack the generator and source board to eight layers, matching the deliverable
onur
2026-09-01 13:26:37 +03:00
-
4fa38e35bd
Fix the RF launch: relieve the planes under J2 and put the ESD on the line
onur
2026-09-01 12:55:49 +03:00
-
1ea2bc64ac
Add the missing TPS2121 status pull-up (R108) and correct the power-mux docs
onur
2026-09-01 12:28:00 +03:00
-
95609a6b6a
Complete the routing: 0 DRC violations, 0 unconnected
onur
2026-09-01 11:58:41 +03:00
-
af7c43b2a8
Restack to four signal layers and route the board
onur
2026-08-16 01:41:43 +03:00
-
b706197667
Initial Ti375 GNSS IMU board design and documentation
main